Basement work contd…

Another long weekend at SJ2W. I went down on Wednesday with my girlfriend who unfortunately had to leave on Friday back up north again. However I spent most of my time down in the basement getting everything ready for the concrete pour. I am not a very patient guy who doesn’t like to ask too much for help, so I ended up mixing the concrete myself which was a bit hard work but after 3.5 hours of continues work all concrete was poured. The result is OK, not as good as I had hoped though since I didn’t get the floor very even but it’s not a problem.

I also bought a MIG/MAG welder today, an American quality brand Miller and it’s a 3-phase 240A so should be pretty useful.